BC Hydro 2025 Call for Power: Overview of Request for Proposal Documents

August 08, 2025

Close

Written By Jessica Kennedy, David Bursey, Ashley White, David Macaulay, Jason Roth and Samantha Chenatte

Further to its April announcement, BC Hydro is moving forward with its 2025 Call for Power (2025 Call). As part of the 2025 Call, BC Hydro issued a request for proposals (RFP) on July 28, 2025. The RFP aims to acquire up to 5,000 GWh/year of electricity from large, clean or renewable projects through partnerships between First Nations and independent power producers (IPP). BC Hydro also issued the RFP documents that proponents must submit to be considered for the 2025 Call (RFP Documents).

Background

The 2025 Call is a competitive energy procurement process that builds on the success of the 2024 Call for Power (2024 Call). Bennett Jones previously discussed the draft RFP documents and the final RFP documents for the 2024 Call (2024 Documents). Following the 2024 Call, BC Hydro awarded ten Electricity Purchase Agreements (EPA) that will provide nearly 5,000 GWh/year of clean, renewable electricity to the province's grid, surpassing their initial target of 3,000 GWh/year.

Before issuing the RFP in the 2025 Call, BC Hydro engaged with IPPs, First Nations and stakeholders from May to July 2025 on its planned approach for the RFP and RFP Documents. This feedback informed the current RFP Documents.

Key Terms of the RFP Documents

The RFP Documents include a Specimen EPA, which details the non-negotiable terms of an EPA between successful proponents and BC Hydro (Specimen EPA). Some key terms from the Specimen EPA are:

Key Changes from the 2024 Documents

The RFP Documents largely parallel the 2024 Documents, with some key changes that emphasize funding opportunities and the importance of economic certainty for project proposals:

Other initiatives remain the same as the 2024 Call, including:

The Specimen EPA largely parallels the 2024 Documents, with some notable changes, including:

RFP Key Dates

Proponents must meet three key dates to participate in the RFP:

RFP results will be announced and EPAs executed in early 2026.

BC's Renewable Energy Strategy

The 2025 Call aligns with the BC government’s broader strategy to accelerate clean energy development, streamline regulatory processes and expand Indigenous participation in the energy sector. As highlighted in recent Bennett Jones commentary, the province is moving toward more frequent and coordinated procurement cycles to meet growing electricity demand and decarbonization goals.

With key deadlines approaching and important changes to the RFP Documents in place, proponents are now working to assess their eligibility and competitiveness under the new framework.

The Bennett Jones team has closely followed and advised on all aspects of BC Hydro’s Calls for Power and the province’s evolving energy policy. Please contact the authors or a member of our Power & Renewables group if you require legal or strategic support in navigating the 2025 Call or related initiatives.